  • Mine production has been in 3 pits, with open pit mining design currently (2020) to depths of 200 meters over 16 years with capacity to process over 1 million tonnes per annum(pa) of ore.
  • ‘Project Crown Jewel’ a 500tph Greenfields project was initiated. The project will see us process all our ore sources on site, namely K1, K2, K3, low grade ore and recrush stockpiles to maximise our diamond recovery.
  • Studies for an underground mine began.